Which of the following activities may, exceptionally, be omitted for an urgent change: 1. Recording that the change has been made 2. Testing the change 3. Holding a CAB meeting 4. Establishing a…
The correct answer is C. 2 and 3. You've hit your limit · resets 12:50am (America/New_York)
Quality Management Systems
Question
Which of the following activities may, exceptionally, be omitted for an urgent change: 1. Recording that the change has been made 2. Testing the change 3. Holding a CAB meeting 4. Establishing a back-out plan
Options
- AAll of them
- B2 and 4
- C2 and 3
- D3 and 4
How the community answered
(33 responses)- A3% (1)
- B9% (3)
- C82% (27)
- D6% (2)
Explanation
You've hit your limit · resets 12:50am (America/New_York)
Topics
#Change Management#urgent change#CAB#back-out plan