CQIA · Question #43

Which of the following activities may, exceptionally, be omitted for an urgent change: 1. Recording that the change has been made 2. Testing the change 3. Holding a CAB meeting 4. Establishing a…

The correct answer is C. 2 and 3. You've hit your limit · resets 12:50am (America/New_York)

Quality Management Systems

Question

Which of the following activities may, exceptionally, be omitted for an urgent change: 1. Recording that the change has been made 2. Testing the change 3. Holding a CAB meeting 4. Establishing a back-out plan

Options

  • AAll of them
  • B2 and 4
  • C2 and 3
  • D3 and 4

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    9% (3)
  • C
    82% (27)
  • D
    6% (2)

Explanation

You've hit your limit · resets 12:50am (America/New_York)

Topics

#Change Management#urgent change#CAB#back-out plan