A business analyst (BA) has executed the last planned workshop in a series in order to verify requirements. All issues have been logged in an issues register. What technique is used to manage and…

The correct answer is A. Item tracking methods. Item tracking methodsare used tolog, track, and resolve outstanding issues related to requirements. The BABOK® Guide (Chapter 5.5 - Assess Requirements Changes)states that item trackingensures accountability and resolution of issuesbefore requirements are finalized.

Requirements Life Cycle Management

Question

A business analyst (BA) has executed the last planned workshop in a series in order to verify requirements. All issues have been logged in an issues register. What technique is used to manage and resolve the outstanding issues?

Options

  • AItem tracking methods
  • BRequirements analysis
  • CRequirements documentation
  • DMetrics and KPIs

How the community answered

(34 responses)
  • A
    88% (30)
  • B
    3% (1)
  • C
    6% (2)
  • D
    3% (1)

Explanation

Item tracking methodsare used tolog, track, and resolve outstanding issues related to requirements. The BABOK® Guide (Chapter 5.5 - Assess Requirements Changes)states that item trackingensures accountability and resolution of issuesbefore requirements are finalized.