A business analyst (BA) has just started a large project and is collaborating with stakeholders to define requirements. Another BA is joining soon to help with this initiative. What action should…

The correct answer is C. Document outcomes of discussions with stakeholders. Documenting stakeholder discussions, elicitation outcomes, and decisionsensures that a new BA can quickly understand the project context. The BABOK® Guide (Chapter 3.5 - Assess Business Analysis Performance)states thatmaintaining documentation enables continuity in business…

Elicitation and Collaboration

Question

A business analyst (BA) has just started a large project and is collaborating with stakeholders to define requirements. Another BA is joining soon to help with this initiative. What action should the BA take to ensure that the new BA understands the project?

Options

  • ARun elicitation sessions in parallel to speed up the process.
  • BDelay elicitation activities until the new BA joins.
  • CDocument outcomes of discussions with stakeholders.
  • DAsk the BA to define the stakeholder engagement approach.

How the community answered

(33 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    88% (29)
  • D
    3% (1)

Explanation

Documenting stakeholder discussions, elicitation outcomes, and decisionsensures that a new BA can quickly understand the project context. The BABOK® Guide (Chapter 3.5 - Assess Business Analysis Performance)states thatmaintaining documentation enables continuity in business analysis activitieseven when new team members join.

Topics

#documentation#knowledge transfer#elicitation outcomes#stakeholder handoff