CCBA · Question #509
A business analyst (BA) has spent the week conducting work sessions with a project's key stakeholders. Together, they have been reviewing user requirements and high-level design flowcharts to ensure…
The correct answer is C. Verifying requirements. The purpose of their work is to verify the requirements. This is because verifying requirements is the process of ensuring that the requirements are correctly defined and documented according to the agreed standards and quality criteria. Verifying requirements can involve…
Question
A business analyst (BA) has spent the week conducting work sessions with a project's key stakeholders. Together, they have been reviewing user requirements and high-level design flowcharts to ensure that they have been correctly defined and documented. Which of the following describes the purpose of their work?
Options
- AValidating requirements
- BEliciting requirements
- CVerifying requirements
- DApproving requirements
How the community answered
(29 responses)- B3% (1)
- C90% (26)
- D7% (2)
Explanation
The purpose of their work is to verify the requirements. This is because verifying requirements is the process of ensuring that the requirements are correctly defined and documented according to the agreed standards and quality criteria. Verifying requirements can involve reviewing user requirements and high-level design flowcharts with the key stakeholders to check for errors, omissions, inconsistencies, or ambiguities. The other options are not as accurate or relevant as verifying requirements.