A business analyst (BA) is working on a project to improve product delivery. The issues arise during the latter stages of the delivery Freecycle and are due to poor communication of the business…
The correct answer is A. Consulted. Consulted is a RACI designation that indicates the stakeholders who need to be consulted before a decision or action is taken1. Consulted can help the BA to improve the communication of the business analysis information from the elicitation phase by involving the testing and…
Question
A business analyst (BA) is working on a project to improve product delivery. The issues arise during the latter stages of the delivery Freecycle and are due to poor communication of the business analysis information from the elicitation phase. As a result, a BA has ensured that the testing and training teams are identified as stakeholders on the RACI Matrix going forward. To which RAG designation should the training and testing teams be added?
Options
- AConsulted
- BResponsible
- CAccountable
- DInformed
How the community answered
(30 responses)- A93% (28)
- C3% (1)
- D3% (1)
Explanation
Consulted is a RACI designation that indicates the stakeholders who need to be consulted before a decision or action is taken1. Consulted can help the BA to improve the communication of the business analysis information from the elicitation phase by involving the testing and training teams in the review and validation of the requirements and designs. By consulting the testing and training teams, the BA can ensure that the requirements and designs are feasible, testable, and aligned with the business needs and objectives2. The other options are not the best RACI designations for the training and testing teams, as they may not reflect their roles and responsibilities in the project. Responsible is a RACI designation that indicates the stakeholders who are assigned to do the work or complete the task3. Accountable is a RACI designation that indicates the stakeholders who have the authority and accountability for the work or task, and who approve the final outcome4. Informed is a RACI designation that indicates the stakeholders who need to be kept informed of the progress or results of the work or task.