nerdexam
IIBA

CCBA · Question #313

A business analyst (BA) is in the process of eliciting requirements. It has been determined that not all requirements can be implemented by the project deadline due to complexity. What must the BA…

The correct answer is D. Maintain requirements based on priority. This is because when the requirements are complex and cannot be implemented by the project deadline, the BA should prioritize the requirements based on their value, urgency, and dependency, and communicate the priority to the project team and the stakeholders. This way, the BA…

Requirements Life Cycle Management

Question

A business analyst (BA) is in the process of eliciting requirements. It has been determined that not all requirements can be implemented by the project deadline due to complexity. What must the BA do to ensure maximum benefit for the stakeholders?

Options

  • AEnsure users are trained based on requirements
  • BApply quality control on requirements
  • CUtilize requirements documentation template
  • DMaintain requirements based on priority

How the community answered

(17 responses)
  • A
    6% (1)
  • D
    94% (16)

Explanation

This is because when the requirements are complex and cannot be implemented by the project deadline, the BA should prioritize the requirements based on their value, urgency, and dependency, and communicate the priority to the project team and the stakeholders. This way, the BA can ensure that the most beneficial requirements are delivered first, and the expectations of the stakeholders are managed. Ensuring users are trained based on requirements (A) is not relevant to the question, as it is a post-implementation activity. Applying quality control on requirements (B) is a good practice, but it does not address the issue of complexity and deadline. Utilizing requirements documentation template ?is not a valid option, as it does not affect the prioritization or implementation of the requirements.

Topics

#requirements prioritization#stakeholder value#deadline management#requirements management

Community Discussion

No community discussion yet for this question.

Full CCBA Practice