nerdexam
IIBA

CCBA · Question #312

A stakeholder would like to add requirements to an IT project which is in flight. The project manager wants to revisit the traceability repository prior to committing to the addition of any new reques

The correct answer is D. Supporting change and scope management. This is because the traceability repository is a tool that helps the BA to track the relationships and dependencies among the requirements, the solution components, and the stakeholders. By using the traceability repository, the BA can assess the impact of any changes or addition

Requirements Life Cycle Management

Question

A stakeholder would like to add requirements to an IT project which is in flight. The project manager wants to revisit the traceability repository prior to committing to the addition of any new requests, because it is used for which of the following activities?

Options

  • ACreating test plans and test cases
  • BApproving requirement relationships
  • CDeveloping documentation for technical support
  • DSupporting change and scope management

How the community answered

(21 responses)
  • B
    5% (1)
  • C
    5% (1)
  • D
    90% (19)

Explanation

This is because the traceability repository is a tool that helps the BA to track the relationships and dependencies among the requirements, the solution components, and the stakeholders. By using the traceability repository, the BA can assess the impact of any changes or additions to the requirements, and manage the scope of the project accordingly. Creating test plans and test cases (A) is not the main purpose of the traceability repository, although it can be used to verify the test coverage and quality of the solution. Approving requirement relationships (B) is not a valid activity, as the requirement relationships are established and documented by the BA, not approved. Developing documentation for technical support ?is not related to the traceability repository, as it is a post- implementation activity.

Topics

#traceability repository#change management#scope management#requirements traceability

Community Discussion

No community discussion yet for this question.

Full CCBA Practice