nerdexam
IIBA

CBAP · Question #98

You are the business analyst for your organization and preparing to complete the requirements elicitation activities. Your manager wants to know when the requirements elicitation process will be compl

The correct answer is D. Eliciting requirements is not a compartmentalized activity.. Requirements elicitation is an iterative, continuous activity that cannot be bounded by a fixed schedule or project size - it recurs throughout the project lifecycle.

Elicitation and Collaboration

Question

You are the business analyst for your organization and preparing to complete the requirements elicitation activities. Your manager wants to know when the requirements elicitation process will be completed. Which of the following responses best describes the nature of the requirements elicitation process?

Options

  • AThe schedule of the project determines the duration of the requirements elicitation process .
  • BThe duration of the requirements elicitation activities is determined by the willingness of the
  • CThe size of the project determines the duration of the requirements elicitation process.
  • DEliciting requirements is not a compartmentalized activity.

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    14% (3)
  • C
    9% (2)
  • D
    73% (16)

Why each option

Requirements elicitation is an iterative, continuous activity that cannot be bounded by a fixed schedule or project size - it recurs throughout the project lifecycle.

AThe schedule of the project determines the duration of the requirements elicitation process .

The project schedule constrains resources allocated to elicitation but does not define when elicitation is functionally complete, since requirements can and do emerge outside scheduled windows.

BThe duration of the requirements elicitation activities is determined by the willingness of the

Stakeholder willingness affects participation quality but is not the defining characteristic that determines the nature or duration of the elicitation process.

CThe size of the project determines the duration of the requirements elicitation process.

Project size influences the scope and complexity of elicitation but does not by itself determine when elicitation ends or characterize the process.

DEliciting requirements is not a compartmentalized activity.Correct

Elicitation is not a compartmentalized, one-time phase because new stakeholders, changing business conditions, and deeper analysis can surface additional requirements at any point. It overlaps with other BA activities such as analysis, design, and validation, making a hard end date artificial. The BABOK describes elicitation as ongoing and intertwined with the full requirements development process.

Concept tested: Iterative and ongoing nature of requirements elicitation

Source: https://www.iiba.org/career-resources/a-business-analysis-professionals-foundation-for-success/babok/

Topics

#elicitation process nature#iterative elicitation#requirements elicitation scope#continuous activity

Community Discussion

No community discussion yet for this question.

Full CBAP Practice