CBAP · Question #97
You are the business analyst for your organization. For the past several months you have been completing the business analysis duties for the solution stakeholders. You now have, you believe, the solu
The correct answer is D. Make certain the stakeholders understand the requirements before they approve the. Before stakeholders can approve requirements, the BA must first ensure they genuinely understand what they are approving - understanding is a prerequisite to valid sign-off.
Question
You are the business analyst for your organization. For the past several months you have been completing the business analysis duties for the solution stakeholders. You now have, you believe, the solution requirements identified and documented. What must you now do with the requirements before proceeding?
Options
- AMake certain the stakeholders can pay for the solution and have them sign off on the
- BPresent the solution to the project manager for his input.
- CGet all of the stakeholders to sign off on the requirements.
- DMake certain the stakeholders understand the requirements before they approve the
How the community answered
(34 responses)- A15% (5)
- B6% (2)
- C3% (1)
- D76% (26)
Why each option
Before stakeholders can approve requirements, the BA must first ensure they genuinely understand what they are approving - understanding is a prerequisite to valid sign-off.
Funding and financial sign-off are concerns for the project sponsor and project manager, not a BA prerequisite before requirements approval.
The project manager does not need to provide input on requirements before stakeholders approve them; requirements approval is a BA-led activity involving solution stakeholders.
Obtaining signatures without confirming understanding is insufficient and violates the principle that approval must be informed - stakeholders may sign off on requirements they do not fully comprehend.
BABOK guidance holds that stakeholders must comprehend requirements before they can meaningfully approve them; approval without understanding produces uninformed sign-off that does not validate the requirements. The BA is responsible for communicating requirements in a way that is clear to each stakeholder group, then confirming comprehension prior to seeking approval. Proceeding without this step risks stakeholders approving a solution that does not meet their actual needs.
Concept tested: Requirements validation and stakeholder approval process
Source: https://www.iiba.org/career-resources/a-business-analysis-professionals-foundation-for-success/babok/