CBAP · Question #505
A business analyst (BA) is eliciting requirements to automate existing manual processes for fulfilling end users service requests. There is pressure from management to automate the process quickly…
The correct answer is A. Perform a gap analysis to understand missing capabilities. Before implementing any COTS solution, the BA must first perform a gap analysis to determine whether the tool's capabilities meet the organization's actual requirements.
Question
A business analyst (BA) is eliciting requirements to automate existing manual processes for fulfilling end users service requests. There is pressure from management to automate the process quickly using a commercial off-the-shelf (COTS) tool. The COTS solution has various modules including one for service request automation that has yet to be implemented in the organization. What e the BA's first step?
Options
- APerform a gap analysis to understand missing capabilities
- BImplement the COTS tool's modules
- CModify the COTS tool to fit the existing process
- DCreate a change strategy
How the community answered
(36 responses)- A78% (28)
- B14% (5)
- C3% (1)
- D6% (2)
Why each option
Before implementing any COTS solution, the BA must first perform a gap analysis to determine whether the tool's capabilities meet the organization's actual requirements.
A gap analysis compares the current state (manual processes) against the desired future state (automated service request fulfillment) and evaluates whether the COTS module bridges that gap. Performing this analysis first ensures the BA understands missing capabilities before any implementation decisions are made. Skipping this step risks deploying a solution that does not fully satisfy the elicited requirements, wasting time and resources.
Implementing the COTS modules before confirming they meet requirements risks deploying an inadequate or misaligned solution.
Modifying a COTS tool to fit existing processes is generally discouraged and should only be considered after a gap analysis confirms that standard modules are insufficient.
Creating a change strategy is a later activity that depends on understanding the gaps first - it cannot be defined without knowing what is missing.
Concept tested: Gap analysis as first step in COTS solution assessment
Source: https://www.iiba.org/career-resources/a-business-analysis-body-of-knowledge/babok/
Topics
Community Discussion
No community discussion yet for this question.