nerdexam
IIBA

CBAP · Question #386

A business analyst (BA) is reviewing the performance results from a recent change initiative. One of the results stated, "The planned schedule expected 50% of the project to be done at milestone 6…

The correct answer is C. Corrective. A corrective action responds to a detected, already-occurring deviation from the plan; the team's overtime was a direct response to an SPI below 1.0, confirming the project was already behind schedule.

Solution Evaluation

Question

A business analyst (BA) is reviewing the performance results from a recent change initiative. One of the results stated, "The planned schedule expected 50% of the project to be done at milestone 6. The schedule performance index (SPI) was .87. Three project team members worked overtime to ensure that the actual schedule would align with the planned schedule." This is an example of what type of action?

Options

  • AEngagement
  • BPreventive
  • CCorrective
  • DImprovement

How the community answered

(21 responses)
  • A
    5% (1)
  • C
    86% (18)
  • D
    10% (2)

Why each option

A corrective action responds to a detected, already-occurring deviation from the plan; the team's overtime was a direct response to an SPI below 1.0, confirming the project was already behind schedule.

AEngagement

Engagement refers to activities designed to involve or motivate stakeholders and is not a category of performance response action used in schedule or cost variance management.

BPreventive

Preventive actions are taken before a deviation materializes, to reduce the likelihood of future problems; here the deviation was already confirmed by the SPI measurement, making any response corrective rather than preventive.

CCorrectiveCorrect

The Schedule Performance Index of 0.87 is a measured indicator that the project was already behind its planned schedule at milestone 6, representing an actual deviation from the baseline. Authorizing overtime to realign actual progress with the plan is the definition of a corrective action - a response taken after a variance has been identified and measured, aimed at bringing performance back in line with the approved plan.

DImprovement

Improvement actions aim to raise performance above the established baseline, not merely restore it to the planned level, which is the sole objective the overtime was designed to achieve.

Concept tested: Corrective action in earned value and schedule management

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#corrective action#schedule performance index#SPI#solution monitoring

Community Discussion

No community discussion yet for this question.

Full CBAP Practice