In performing the task of planning for business analysis governance for a software implementation project, the business analyst (BA) recommends that prioritization of requirements be done based on…

The correct answer is C. Time Boxing. Time boxing or budgeting prioritizes business analysis information based on the allocation of a fixed resource. It is frequently used when the solution approach has been determined. Time boxing is used to prioritize requirements based on the amount of work that the project team…

Requirements Life Cycle Management

Question

In performing the task of planning for business analysis governance for a software implementation project, the business analyst (BA) recommends that prioritization of requirements be done based on the amount of work that the project team is capable of delivering in a given period of time. Which of the following techniques is the BA recommending?

Options

  • ANegotiation
  • BGrouping
  • CTime Boxing
  • DBudgeting

How the community answered

(66 responses)
  • A
    15% (10)
  • B
    3% (2)
  • C
    76% (50)
  • D
    6% (4)

Explanation

Time boxing or budgeting prioritizes business analysis information based on the allocation of a fixed resource. It is frequently used when the solution approach has been determined. Time boxing is used to prioritize requirements based on the amount of work that the project team is capable of delivering in a set period of time. Budgeting is used when the project team has been allocated a fixed amount of money. This approach is most often used when a fixed deadline must be met or for solutions that are enhanced on a regular and frequent basis.

Topics

#time boxing#requirements prioritization#governance planning#capacity-based prioritization