CBAP · Question #343
While defining what necessary conditions are required to achieve the business need for a highly regulated government client, a business analyst (BA) discovers that some legacy policies will either…
The correct answer is B. Identify an assumption about future state value. When legacy policies constrain or are insufficient to achieve the desired future state for a regulated client, the BA should classify the expected future state value as an assumption to flag the uncertainty for stakeholders.
Question
While defining what necessary conditions are required to achieve the business need for a highly regulated government client, a business analyst (BA) discovers that some legacy policies will either constrain or are insufficient to achieve value desired by the future state. How should the BA proceed?
Options
- AModify the solution to comply with the policies
- BIdentify an assumption about future state value
- CModel two future states, one with and another without these policies
- DObtain approval to change the policies
How the community answered
(61 responses)- A3% (2)
- B75% (46)
- C7% (4)
- D15% (9)
Why each option
When legacy policies constrain or are insufficient to achieve the desired future state for a regulated client, the BA should classify the expected future state value as an assumption to flag the uncertainty for stakeholders.
Modifying the solution to comply with constraining policies may sacrifice the intended business value and does not address policies that are insufficient to support the future state at all.
In BABOK terms, when policy constraints create uncertainty about whether the full desired value can be realized, the BA should document the future state value as an assumption - a factor believed to be true but not yet confirmed. This is appropriate because the constrained policy environment means the value outcome cannot be guaranteed, and labeling it as an assumption formally flags the dependency for sponsors and stakeholders. Documenting the assumption allows future state definition to proceed while ensuring the policy risk remains visible.
Modeling two alternative future states adds scope and complexity beyond what is needed at this stage; the BA's task is to define necessary conditions and surface constraints, not to design multiple scenarios.
Obtaining approval to change government policies is outside the BA's authority and is not a feasible course of action during the requirements definition phase of the project.
Concept tested: Documenting policy constraints as assumptions in BA planning