CBAP · Question #321
There are four inputs to the evaluate solution performance process. Which one of the following is not an input to the evaluate solution performance process?
The correct answer is A. BA Management Plan. The BA Management Plan is not an input to the Evaluate Solution Performance process; the inputs are focused on the solution itself, its defects, and requirements.
Question
There are four inputs to the evaluate solution performance process. Which one of the following is not an input to the evaluate solution performance process?
Options
- ABA Management Plan
- BRequirements
- CDefects
- DSolution
How the community answered
(29 responses)- A76% (22)
- B14% (4)
- C7% (2)
- D3% (1)
Why each option
The BA Management Plan is not an input to the Evaluate Solution Performance process; the inputs are focused on the solution itself, its defects, and requirements.
The BA Management Plan is an output of Business Analysis Planning and Monitoring that guides how BA work is conducted overall - it is not consumed as an input when evaluating how well a solution performs. The Evaluate Solution Performance task requires artifacts that directly reflect solution behavior and expectations, such as the solution, requirements, and defects.
Requirements are a valid input because they establish the performance baseline against which the actual solution behavior is compared.
Defects are a valid input because they represent identified gaps between expected and actual solution performance and must be analyzed during evaluation.
The Solution is a direct input because it is the physical or operational artifact being assessed to determine whether it meets business objectives.
Concept tested: Inputs to Evaluate Solution Performance task in BABOK
Source: https://www.iiba.org/career-resources/a-business-analysis-body-of-knowledge/