CBAP · Question #322

There are four inputs to the plan requirements management process. Which one of the following is not an input to the plan requirements management process?

The correct answer is D. Requirements. Requirements are not an input to Plan Requirements Management because this planning task occurs before requirements are elicited, defining how they will be handled rather than using them.

Business Analysis Planning and Monitoring

Question

There are four inputs to the plan requirements management process. Which one of the following is not an input to the plan requirements management process?

Options

  • ABusiness Analysis Approach
  • BBA Plan(s)
  • COrganizational Process Assets
  • DRequirements

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    11% (4)
  • D
    80% (28)

Why each option

Requirements are not an input to Plan Requirements Management because this planning task occurs before requirements are elicited, defining how they will be handled rather than using them.

ABusiness Analysis Approach

The Business Analysis Approach is a valid input because it defines the overall methodology and strategy that directly shapes how requirements management will be planned.

BBA Plan(s)

BA Plans are valid inputs because existing business analysis planning documents provide constraints, standards, and context that inform requirements management planning.

COrganizational Process Assets

Organizational Process Assets are valid inputs because they supply templates, historical lessons learned, and organizational standards that guide how requirements management should be structured.

DRequirementsCorrect

Plan Requirements Management is a forward-looking planning task that establishes how requirements will be traced, maintained, prioritized, and approved throughout the project - the actual requirements do not yet exist as formalized artifacts at this stage. The inputs to this task are planning and organizational documents that provide context for structuring the requirements management approach.

Concept tested: Inputs to Plan Requirements Management task in BABOK

Source: https://www.iiba.org/career-resources/a-business-analysis-body-of-knowledge/

Topics

#requirements management plan#process inputs#BABOK#planning