CBAP · Question #292
Which of the following processes is used to make certain that the project team members are completing the project work according to the project plan?
The correct answer is D. Quality control. Quality control is the process of monitoring and inspecting project work results to verify that team members are completing work according to the project plan and defined quality standards.
Question
Which of the following processes is used to make certain that the project team members are completing the project work according to the project plan?
Options
- AProject time management
- BProject scope management
- CQuality management plan
- DQuality control
How the community answered
(36 responses)- A6% (2)
- B11% (4)
- C3% (1)
- D81% (29)
Why each option
Quality control is the process of monitoring and inspecting project work results to verify that team members are completing work according to the project plan and defined quality standards.
Project time management is a knowledge area concerned with planning and controlling the project schedule, not verifying work conformance to the project plan.
Project scope management governs what is and is not included in the project, not the inspection of work execution against the plan.
A quality management plan is a planning document that defines how quality will be managed; it is not a process used to verify that work is being completed correctly.
Quality control involves measuring specific project results and deliverables to determine whether they comply with the quality standards defined in the quality management plan. It is an execution-phase process focused on identifying defects and variances, ensuring the project team's outputs conform to planned requirements before acceptance.
Concept tested: Quality control process for monitoring work conformance
Source: https://www.pmi.org/learning/library/quality-control-project-management-6370