CBAP · Question #293
Which of the following is concerned with determining whether the information used for risk analysis is probable, of high class, or accurate?
The correct answer is D. Risk Data Quality Assessment. Risk Data Quality Assessment evaluates whether the data used in risk analysis is accurate, reliable, and sufficient to support sound decision-making.
Question
Which of the following is concerned with determining whether the information used for risk analysis is probable, of high class, or accurate?
Options
- ARisk Urgency Assessment
- BRisk Probability and Impact Assessment
- CRisk Categorization
- DRisk Data Quality Assessment
How the community answered
(37 responses)- A8% (3)
- B14% (5)
- C5% (2)
- D73% (27)
Why each option
Risk Data Quality Assessment evaluates whether the data used in risk analysis is accurate, reliable, and sufficient to support sound decision-making.
Risk Urgency Assessment ranks risks based on how quickly a response is needed, not on the quality or reliability of the data behind those risks.
Risk Probability and Impact Assessment measures how likely a risk is to occur and what its consequences would be, not whether the underlying data is credible.
Risk Categorization groups identified risks by source, area, or phase to improve organization and analysis structure, not to validate data quality.
Risk Data Quality Assessment is the process of examining how reliable and accurate the information underpinning risk analysis is, considering factors such as integrity, availability, and the degree to which it is understood. It ensures that risk analysis conclusions are not built on incomplete or biased data, making it the direct match for the question's focus on probability, class, and accuracy of risk information.
Concept tested: Risk data quality evaluation in risk management
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok