SAP
C_TSCM42_64 · Question #43
Which one of the following scheduling types cannot be assigned as default to an order type (production order)?
The correct answer is A. Midpoint. See the full explanation below for the reasoning.
Question
Which one of the following scheduling types cannot be assigned as default to an order type (production order)?
Options
- AMidpoint
- BForward
- COnly capacity requirements
- DBackward
How the community answered
(32 responses)- A81% (26)
- B6% (2)
- C9% (3)
- D3% (1)
Community Discussion
No community discussion yet for this question.