The correct answer is C. 5.6 hours. SAP C_TSCM42_64 Exam

Question

In SAP ECC, you calculate the standard available capacity for a work center capacity with the following data: start: 7:00:00 a.m., end. 3:00:00 p.m., break duration: 1 hour, rate of utilization: 80%, overload. 110%, number of individual capacities: 1. How large is the standard available capacity?

Options

  • A7 hours
  • B8 hours
  • C5.6 hours
  • D6.16 hours

Explanation

SAP C_TSCM42_64 Exam

Community Discussion

No community discussion yet for this question.