Question
A finished material is to be planned in a controlled manner in the SAP ECC system in the context of requirements planning. The planned orders are scheduled using what is known as basic date scheduling (not lead-time scheduling). Which of the following statements is true for the resulting dependent requirements?
Options
- AWhen a customer order is created for the finished product, the dependent requirements are
- BIn multi-level backward scheduling, dependent requirements are triggered at the start date for
- CIn multi-level backward scheduling, dependent requirements are triggered at the start date for
- DIf individual material components are explicitly assigned to operations during BOM and routing