nerdexam
SAP

C_TSCM42_64 · Question #47

The company that you advise does not want to manage certain value-intensive materials in the warehouse stock. Instead, the user wishes to control material provision in such a way that these…

The correct answer is B. Using the special procurement key direct procurement/external procurement in the material master for C. Using the item type non-stock item in the bill of material for the material in question. See the full explanation below for the reasoning.

Question

The company that you advise does not want to manage certain value-intensive materials in the warehouse stock. Instead, the user wishes to control material provision in such a way that these materials are procured directly for the production and/or process order. How can you fulfill this request? (Choose two.)

Options

  • AUsing the special procurement key subcontracting in the material master for the component
  • BUsing the special procurement key direct procurement/external procurement in the material master for
  • CUsing the item type non-stock item in the bill of material for the material in question
  • DUsing the procurement type external procurement in the material master for the component
  • EControlling the material in question as a co-product

How the community answered

(39 responses)
  • A
    5% (2)
  • B
    85% (33)
  • D
    8% (3)
  • E
    3% (1)

Community Discussion

No community discussion yet for this question.

Full C_TSCM42_64 Practice