For a specific end product, you want to use a planning time fence and fixing type 1 to ensure that the planning situation in SAP ECC calms down in a short-term time window. Two customer orders…

The correct answer is B. Newly created planned orders cannot be created by requirements planning before the end of. See the full explanation below for the reasoning.

Question

For a specific end product, you want to use a planning time fence and fixing type 1 to ensure that the planning situation in SAP ECC calms down in a short-term time window. Two customer orders arrive at short notice and their receipts should really be within the planning time fence, due to their date/time. Which statement is true with this scenario?

Options

  • AWithin the planning time fence, the newly created planned orders are automatically frozen by
  • BNewly created planned orders cannot be created by requirements planning before the end of
  • CThe MRP controller has no possibility of creating planned orders within the planning time fence.
  • DRequirements planning only examines changes that are relevant to scheduling within the planning

How the community answered

(44 responses)
  • A
    2% (1)
  • B
    82% (36)
  • C
    5% (2)
  • D
    11% (5)