C_TSCM42_64 · Question #44
In your enterprise, a planning strategy is used in SAP ECC that enables joint planning of all MRP scheduled assemblies for a finished product to trigger procurement of these assemblies. It is…
The correct answer is D. Planning without final assembly (strategy 50). See the full explanation below for the reasoning.
Question
In your enterprise, a planning strategy is used in SAP ECC that enables joint planning of all MRP scheduled assemblies for a finished product to trigger procurement of these assemblies. It is important to ensure that the finished product is only produced when there is a customer order present. When a customer order is received, production of the finished product should be triggered in the form of make-to-order planning and production. Which planning strategy covers this scenario?
Options
- APlanning with make-to-stock (strategy 10)
- BPlanning at the assembly level (strategy 70)
- CPlanning with final assembly (strategy 40)
- DPlanning without final assembly (strategy 50)
How the community answered
(40 responses)- A8% (3)
- B3% (1)
- C5% (2)
- D85% (34)