C_TSCM42_64 · Question #42
A customer wishes to only produce a finished product when customer orders for it are present. Final assembly should then be carried out at short notice in make-to-order production. Up until this…
The correct answer is C. The finished product uses strategy 20 (make-to-order production) and all the important assemblies D. The finished product uses strategy 50 (planning without final assembly) and all the assemblies in the. See the full explanation below for the reasoning.
Question
A customer wishes to only produce a finished product when customer orders for it are present. Final assembly should then be carried out at short notice in make-to-order production. Up until this point, the important assemblies needed in final assembly should already be available in stock. Provision of these assemblies should therefore be triggered by planning. Which options could you offer the customer as useful alternatives in SAP ECC? (Choose two.)
Options
- AThe finished product uses strategy 40 (planning with final assembly) and all the important assemblies
- BThe finished product uses strategy 30 (production by lots) and all the important assemblies in the
- CThe finished product uses strategy 20 (make-to-order production) and all the important assemblies
- DThe finished product uses strategy 50 (planning without final assembly) and all the assemblies in the
How the community answered
(42 responses)- A19% (8)
- B10% (4)
- C71% (30)