C_TPLM22_64 · Question #52

Assume you have created a sales order for a material to which a strategy group for assembly processing has been assigned and the system automatically created a so-called assembly order in the…

The correct answer is C. MRP Planning stage. See the full explanation below for the reasoning.

Question

Assume you have created a sales order for a material to which a strategy group for assembly processing has been assigned and the system automatically created a so-called assembly order in the background and started assembly processing. In this case, the assembly processing omits which stage and generates an operative order directly from the sales order? Please choose the correct answer.

Options

  • ADelivery stage
  • BScheduling stage
  • CMRP Planning stage
  • DBilling stage

How the community answered

(50 responses)
  • A
    4% (2)
  • B
    10% (5)
  • C
    82% (41)
  • D
    4% (2)

Community Discussion

No community discussion yet for this question.