C_TPLM22_64 · Question #51

Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing? There are 2 correct answers to this question.

The correct answer is A. Create a billing plan assigned to a sales order item. C. Activate indicator sales document date for milestones. See the full explanation below for the reasoning.

Question

Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing? There are 2 correct answers to this question.

Options

  • ACreate a billing plan assigned to a sales order item.
  • BSet up percentage of completion for milestones.
  • CActivate indicator sales document date for milestones.
  • DCreate a billing plan assigned to a WBS element.
  • EActivate milestone functions.

How the community answered

(31 responses)
  • A
    77% (24)
  • B
    3% (1)
  • D
    13% (4)
  • E
    6% (2)

Community Discussion

No community discussion yet for this question.