Which indicator is set for assemblies that need to be ordered well in advance of consumption and are allocated as stock items? Please choose the correct answer.

The correct answer is B. Planned independent requirement. See the full explanation below for the reasoning.

Question

Which indicator is set for assemblies that need to be ordered well in advance of consumption and are allocated as stock items? Please choose the correct answer.

Options

  • AThird party purchase requisition
  • BPlanned independent requirement
  • CPreliminary purchase requisition
  • DPlanned purchase requisition

How the community answered

(45 responses)
  • A
    4% (2)
  • B
    84% (38)
  • C
    2% (1)
  • D
    9% (4)