Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity? There are 3 correct answers to this question.

The correct answer is A. A distribution key must be maintained in the work center B. Scheduling must have been carried D. A work center must be maintained in the activity. See the full explanation below for the reasoning.

Question

Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity? There are 3 correct answers to this question.

Options

  • AA distribution key must be maintained in the work center
  • BScheduling must have been carried
  • CThe capacity requirements indicator must not be set in the network header
  • DA work center must be maintained in the activity

How the community answered

(43 responses)
  • A
    77% (33)
  • C
    23% (10)