Which of the following information regarding cost activity is not relevant for the calculation of planned costs? Please choose the correct answer.
The correct answer is D. Cost activities based on external services. See the full explanation below for the reasoning.
Question
Which of the following information regarding cost activity is not relevant for the calculation of planned costs? Please choose the correct answer.
Options
- AThe cost element is defaulted for cost activities based on the network profile
- BA unit costing that enables detailed planning with multiple cost elements, or an invoicing plan
- CControl key
- DCost activities based on external services
How the community answered
(55 responses)- A5% (3)
- B4% (2)
- C13% (7)
- D78% (43)