SAP
C_TPLM22_64 · Question #68
Which indicator do you use to define the characteristics of a WBS element and to specify tasks that are performed by the WBS element when the project is executed? Please choose the correct answer.
The correct answer is C. Operative indicators. See the full explanation below for the reasoning.
Question
Which indicator do you use to define the characteristics of a WBS element and to specify tasks that are performed by the WBS element when the project is executed? Please choose the correct answer.
Options
- ACost indicators
- BBilling indicators
- COperative indicators
- DProject cost indicators
How the community answered
(51 responses)- A8% (4)
- B16% (8)
- C71% (36)
- D6% (3)
Community Discussion
No community discussion yet for this question.