Which indicator do you use to define the characteristics of a WBS element and to specify tasks that are performed by the WBS element when the project is executed? Please choose the correct answer.

The correct answer is C. Operative indicators. See the full explanation below for the reasoning.

Question

Which indicator do you use to define the characteristics of a WBS element and to specify tasks that are performed by the WBS element when the project is executed? Please choose the correct answer.

Options

  • ACost indicators
  • BBilling indicators
  • COperative indicators
  • DProject cost indicators

How the community answered

(51 responses)
  • A
    8% (4)
  • B
    16% (8)
  • C
    71% (36)
  • D
    6% (3)