C_TPLM22_64 · Question #44
What is the starting point for milestone billing? Please choose the correct answer.
The correct answer is D. Sales order item with a billing plan. See the full explanation below for the reasoning.
Question
What is the starting point for milestone billing? Please choose the correct answer.
Options
- APurchase order
- BPurchase requisition
- CGoods receipt
- DSales order item with a billing plan
How the community answered
(48 responses)- A10% (5)
- B4% (2)
- C6% (3)
- D79% (38)