C_TPLM22_64 · Question #45
Most of the reports in the SAP Project System can be refreshed without exiting or closing the report. Which report must be restarted to update the displayed data? Please choose the correct the answer.
The correct answer is C. Hierarchical Reports. See the full explanation below for the reasoning.
Question
Most of the reports in the SAP Project System can be refreshed without exiting or closing the report. Which report must be restarted to update the displayed data? Please choose the correct the answer.
Options
- AIndividual Overviews
- BStructure Overview
- CHierarchical Reports
- DReports by Cost Element
How the community answered
(22 responses)- A5% (1)
- B5% (1)
- C77% (17)
- D14% (3)