C_TPLM22_64 · Question #53

How can you determine the degree of control yourself if you are managing material in plant stock or according to individual WBS element where you have no control over procurement or fully…

The correct answer is A. Requirements grouping. See the full explanation below for the reasoning.

Question

How can you determine the degree of control yourself if you are managing material in plant stock or according to individual WBS element where you have no control over procurement or fully responsible for procurement? Please choose the correct answer.

Options

  • ARequirements grouping
  • BRequirements controlling
  • CProject grouping
  • DWBS grouping

How the community answered

(49 responses)
  • A
    82% (40)
  • B
    10% (5)
  • C
    4% (2)
  • D
    4% (2)

Community Discussion

No community discussion yet for this question.