A company has assets at multiple locations that require maintenance. There is a requirement to have a single work order with charges rolled up to a single GL account. How can that be achieved?

The correct answer is B. Create a child work order for each asset. e1ec-4709-8b27-4937d78f9909/document/ec94eee2-7378-4241-a9c2-62499183955a/media

Work Management

Question

A company has assets at multiple locations that require maintenance. There is a requirement to have a single work order with charges rolled up to a single GL account. How can that be achieved?

Options

  • ACreate a task work order for each asset.
  • BCreate a child work order for each asset.
  • CAdd a job plan that has the assets associated.
  • DAdd the assets in Multiple Assets, Locations and Cls.

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    70% (14)
  • C
    5% (1)
  • D
    20% (4)

Explanation

e1ec-4709-8b27-4937d78f9909/document/ec94eee2-7378-4241-a9c2-62499183955a/media

Topics

#child work orders#GL accounts#multiple assets#work order hierarchy