A company has multiple crews that work different days and hours. The administrator must define these work schedules. Where can this be done?
The correct answer is D. Define/Apply Shifts in the Calendars application. a181d6155e3a/entry/ From_The_Maximo_Support_Desk_Introduction_To_Using_Crews_On_Work_Orders?lang=en
Work Management
Question
A company has multiple crews that work different days and hours. The administrator must define these work schedules. Where can this be done?
Options
- ACrew Definition in the Labor application
- BDefine/Apply Shifts in the Crews application
- CCrew Definition in the Calendars application
- DDefine/Apply Shifts in the Calendars application
How the community answered
(34 responses)- A9% (3)
- B6% (2)
- C3% (1)
- D82% (28)
Explanation
a181d6155e3a/entry/ From_The_Maximo_Support_Desk_Introduction_To_Using_Crews_On_Work_Orders?lang=en
Topics
#crew scheduling#shift definition#calendars application#work schedules