nerdexam
IBM

C2010-555 · Question #72

C2010-555 Question #72: Real Exam Question with Answer & Explanation

Sign in or unlock C2010-555 to reveal the answer and full explanation for question #72. The question stem and answer options stay visible for context.

Question

A technician has completed a job and observed that more work is needed on the same asset. A new record is required to have the same asset, location and GL account. What action needs to be taken?

Options

  • ASelect Create Follow-up action from the completed work order
  • BSelect Create Work Order action from the completed work order
  • CSelect Create Work Package action from the completed work order
  • DClick on the Plans tab, and add a new child work order from the completed work order

Unlock C2010-555 to see the answer

You've previewed enough free C2010-555 questions. Unlock C2010-555 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full C2010-555 Practice