After a job plan has been applied to a work order the user finds that 2 more tasks are required to perform the work on the work order. How does the user add those 2 tasks?
The correct answer is B. Add the tasks directly on the work order's Plans table. _tasks_job_plans.html
Work Management
Question
After a job plan has been applied to a work order the user finds that 2 more tasks are required to perform the work on the work order. How does the user add those 2 tasks?
Options
- AAdd the tasks to a follow up job plan
- BAdd the tasks directly on the work order's Plans table
- CChange the job plan's status to INACTIVE and add the tasks
- DCreate a new job plan revision and add the tasks to the new revision
How the community answered
(28 responses)- A7% (2)
- B71% (20)
- C4% (1)
- D18% (5)
Explanation
_tasks_job_plans.html
Topics
#work order tasks#job plan#plans tab#task management