Question

After a job plan has been applied to a work order the user finds that 2 more tasks are required to perform the work on the work order. How does the user add those 2 tasks?

Options

  • AAdd the tasks to a follow up job plan
  • BAdd the tasks directly on the work order's Plans table
  • CChange the job plan's status to INACTIVE and add the tasks
  • DCreate a new job plan revision and add the tasks to the new revision

Explanation

_tasks_job_plans.html