C2010-555 · Question #38

A company has identified three tasks (10, 20 and 30) and these tasks must be accomplished in a specific order to prevent damage to the asset. Task 10 must be complete before task 20 can begin, task…

The correct answer is C. Enable Flow Control on the Work order and identify the sequence for each task in the. ftp://ftp.software.ibm.com/software/iea/content/com.ibm.iea.mam/mam/7.1/work_management/co nfig_auto_wo_status_change.pdf

Work Management

Question

A company has identified three tasks (10, 20 and 30) and these tasks must be accomplished in a specific order to prevent damage to the asset. Task 10 must be complete before task 20 can begin, task 20 must be complete before task 30 can begin. How can the planner facilitate this requirement?

Options

  • AUse the Sequence Column to identity the sequence
  • BEnable Flow Control on the Work Order and use the Sequence Column to identify the sequence
  • CEnable Flow Control on the Work order and identify the sequence for each task in the
  • DUse the Sequence Column to identify the sequence and setup Flow Actions that change the task

How the community answered

(39 responses)
  • A
    13% (5)
  • B
    8% (3)
  • C
    77% (30)
  • D
    3% (1)

Explanation

ftp://ftp.software.ibm.com/software/iea/content/com.ibm.iea.mam/mam/7.1/work_management/co nfig_auto_wo_status_change.pdf

Topics

#flow control#task sequencing#work order tasks#task dependencies