C2010-555 · Question #134

A company is using Process Flow Control to ensure the tasks are done in the proper order. By default, which status indicated the next task to be worked on?

The correct answer is C. INPRG. mon/c_wo_status.html

Work Management

Question

A company is using Process Flow Control to ensure the tasks are done in the proper order. By default, which status indicated the next task to be worked on?

Options

  • AAPRP
  • BCOMP
  • CINPRG
  • DWPCOND

How the community answered

(39 responses)
  • A
    15% (6)
  • B
    5% (2)
  • C
    77% (30)
  • D
    3% (1)

Explanation

mon/c_wo_status.html

Topics

#Process Flow Control#task sequencing#INPRG status#work order status