A company is using Process Flow Control to ensure the tasks are done in the proper order. By default, which status indicated the next task to be worked on?
The correct answer is C. INPRG. mon/c_wo_status.html
Work Management
Question
A company is using Process Flow Control to ensure the tasks are done in the proper order. By default, which status indicated the next task to be worked on?
Options
- AAPRP
- BCOMP
- CINPRG
- DWPCOND
How the community answered
(39 responses)- A15% (6)
- B5% (2)
- C77% (30)
- D3% (1)
Explanation
mon/c_wo_status.html
Topics
#Process Flow Control#task sequencing#INPRG status#work order status