What is an objective of the process Change management?
The correct answer is A. making the correct decisions on the implementation of changes to the information provisioning. Change Management exists to ensure that changes to information provisioning are evaluated and decided upon correctly before implementation begins - making option A correct. The process is fundamentally about governance and decision-making: determining whether and how a change…
Question
What is an objective of the process Change management?
Options
- Amaking the correct decisions on the implementation of changes to the information provisioning
- Bdetailed monitoring of the progress of the changes
- Cmanaging the implementation of the changes
How the community answered
(33 responses)- A82% (27)
- B12% (4)
- C6% (2)
Explanation
Change Management exists to ensure that changes to information provisioning are evaluated and decided upon correctly before implementation begins - making option A correct. The process is fundamentally about governance and decision-making: determining whether and how a change should be approved, not the act of carrying it out.
Option B (detailed monitoring of progress) describes activities that belong to project management or operational management, which track execution after a decision is made. Option C (managing the implementation) is the role of release or implementation management, which handles the actual rollout of approved changes - Change Management hands off to those processes, it doesn't own them.
Memory tip: Think of Change Management as the boardroom, not the construction site. It makes the call on whether a change is safe and justified; other processes do the building and the inspecting.