BIMF.EN · Question #46
What is not an activity of Contract management?
The correct answer is B. changing the time of delivery of a change. Option B belongs to Change Management, not Contract Management - adjusting the timing of a change delivery is handled by the Change Management process, which governs the scheduling and implementation of changes to IT services. Option A (agreeing on communication protocols…
Question
What is not an activity of Contract management?
Options
- Aagreeing on how the information manager is to communicate with the IT director
- Bchanging the time of delivery of a change
- Cmonitoring whether the supplied IT-services correspond to the agreed services
How the community answered
(38 responses)- A11% (4)
- B71% (27)
- C18% (7)
Explanation
Option B belongs to Change Management, not Contract Management - adjusting the timing of a change delivery is handled by the Change Management process, which governs the scheduling and implementation of changes to IT services.
Option A (agreeing on communication protocols between the information manager and IT director) is a Contract Management activity, as establishing governance and communication arrangements between parties is a core part of managing contractual relationships.
Option C (monitoring whether supplied IT services match agreed services) is also a Contract Management activity - verifying that the supplier delivers what was contractually agreed is perhaps the most fundamental duty of Contract Management.
Memory tip: Think of Contract Management as everything that lives inside the contract - what was agreed, who communicates how, and whether delivery matches the agreement. Anything about changing a service delivery schedule points to Change Management instead.