BA-201 · Question #214
The business analyst (0A) at Universal Containers has met with stakeholders and is using the waterfall methodology to capture requirements for Sales Cloud enhancements for a future product release. Wh
The correct answer is B. Get approval and signoff on the requirements.. This answer states that getting approval and signoff on the requirements is the next step for the BA to take before build can begin. Approval and signoff on the requirements means that the stakeholders agree that the requirements are accurate, complete, and feasible, and that the
Question
The business analyst (0A) at Universal Containers has met with stakeholders and is using the waterfall methodology to capture requirements for Sales Cloud enhancements for a future product release. What is the next step for the BA to take before build can begin?
Options
- ADefine the minimal viable product.
- BGet approval and signoff on the requirements.
- CSchedule sprint planning meetings.
How the community answered
(55 responses)- A5% (3)
- B80% (44)
- C15% (8)
Explanation
This answer states that getting approval and signoff on the requirements is the next step for the BA to take before build can begin. Approval and signoff on the requirements means that the stakeholders agree that the requirements are accurate, complete, and feasible, and that they authorize the development team to start building the solution. Approval and signoff on the requirements helps to avoid scope creep, rework, and miscommunication. https://trailhead.salesforce.com/en/content/learn/modules/salesforce-business-analyst- certification-prep/prepare-for-the-salesforce-business-analyst-certification-exam