74-343 · Question #94

74-343 Question #94: Real Exam Question with Answer & Explanation

Sign in or unlock 74-343 to reveal the answer and full explanation for question #94. The question stem and answer options stay visible for context.

Question

Your company uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks. You create a task with no duration, start, or finish date, and then you assign a resource. Later, you enter a duration of three days for that task. You need to let the resource know how the Work will be affected. What should you say?

Options

  • AWork will increase to 24 hours.
  • BWork will remain at 0 hours.
  • CWork will increase to 16 hours.
  • DWork will remain at 8 hours.

Unlock 74-343 to see the answer

You've previewed enough free 74-343 questions. Unlock 74-343 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full 74-343 Practice