Your company uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks. You create a task with no duration, start, or finish date, and then you…
The correct answer is A. Work will increase to 24 hours. See the full explanation below for the reasoning.
Question
Your company uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks. You create a task with no duration, start, or finish date, and then you assign a resource. Later, you enter a duration of three days for that task. You need to let the resource know how the Work will be affected. What should you say?
Options
- AWork will increase to 24 hours.
- BWork will remain at 0 hours.
- CWork will increase to 16 hours.
- DWork will remain at 8 hours.
How the community answered
(53 responses)- A83% (44)
- B9% (5)
- C2% (1)
- D6% (3)