74-343 · Question #94
74-343 Question #94: Real Exam Question with Answer & Explanation
Sign in or unlock 74-343 to reveal the answer and full explanation for question #94. The question stem and answer options stay visible for context.
Question
Your company uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks. You create a task with no duration, start, or finish date, and then you assign a resource. Later, you enter a duration of three days for that task. You need to let the resource know how the Work will be affected. What should you say?
Options
- AWork will increase to 24 hours.
- BWork will remain at 0 hours.
- CWork will increase to 16 hours.
- DWork will remain at 8 hours.