74-343 · Question #90

Your company uses Project Standard 2013 to track project progress. You need to accurately calculate cost performance index (CPI) as a health indicator. Which three actions should you perform? (Each…

The correct answer is A. Ensure there is a value in the Status Date field. B. Ensure there is a value in the Standard Rate field. D. Enter actual progress information. See the full explanation below for the reasoning.

Question

Your company uses Project Standard 2013 to track project progress. You need to accurately calculate cost performance index (CPI) as a health indicator. Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)

Options

  • AEnsure there is a value in the Status Date field.
  • BEnsure there is a value in the Standard Rate field.
  • CEnsure Task Dependencies exist in the schedule.
  • DEnter actual progress information.
  • ELevel resources within available slack.

How the community answered

(27 responses)
  • A
    74% (20)
  • C
    7% (2)
  • E
    19% (5)