220-1202 · Question #3
A network technician notices that most of the company's network switches are now end-of-life and need to be upgraded. Which of the following should the technician do first?
The correct answer is C. Propose the change. In a structured change-management process, the very first step is to propose (or formally request) the change via a Request for Change (RFC). This ensures stakeholders review the need, assess risks, and determine the priority before any approvals, scheduling, or implementation…
Question
A network technician notices that most of the company's network switches are now end-of-life and need to be upgraded. Which of the following should the technician do first?
Options
- AImplement the change
- BApprove the change.
- CPropose the change.
- DSchedule the change.
How the community answered
(31 responses)- A6% (2)
- B6% (2)
- C84% (26)
- D3% (1)
Explanation
In a structured change-management process, the very first step is to propose (or formally request) the change via a Request for Change (RFC). This ensures stakeholders review the need, assess risks, and determine the priority before any approvals, scheduling, or implementation occur.