220-1002 · Question #620

A technician is implementing a change to a piece of production environment. The change is causing other several other problem to occur. Which of the following should the technician do NEXT?

The correct answer is B. Attempt to recreate the issues in the QA environment troubleshoot them quickly. When a production change introduces unexpected problems, the technician should attempt to reproduce and diagnose the issues in a QA (Quality Assurance) or test environment as quickly as possible. This isolates the root cause without further disrupting production and allows…

Hardware and network troubleshooting

Question

A technician is implementing a change to a piece of production environment. The change is causing other several other problem to occur. Which of the following should the technician do NEXT?

Options

  • AComplete the change to the prod ction environment within the allotted time frame.
  • BAttempt to recreate the issues in the QA environment troubleshoot them quickly.
  • CBegin following the back-out plan that was outlined in the planning meeting.
  • DComplete a risk analysis of the new changes and their potential impact on other systems.

How the community answered

(65 responses)
  • A
    6% (4)
  • B
    83% (54)
  • C
    2% (1)
  • D
    9% (6)

Explanation

When a production change introduces unexpected problems, the technician should attempt to reproduce and diagnose the issues in a QA (Quality Assurance) or test environment as quickly as possible. This isolates the root cause without further disrupting production and allows troubleshooting without risk. Reproducing the issue in QA can quickly confirm whether the change itself is the cause and guide a targeted fix or rollback decision. Completing the change despite active problems (A) risks compounding damage. Simply executing the back-out plan (C) without understanding the cause may be appropriate if quick resolution is impossible, but diagnosing first allows for a more informed decision. Performing a risk analysis (D) is a planning step that should have been done before the change was implemented, not after problems have already appeared in production.

Topics

#change management#back-out plan#production environment#risk management