220-1002 · Question #518
220-1002 Question #518: Real Exam Question with Answer & Explanation
The correct answer is C: Scoping the change. Change management requires that any approved change be limited strictly to its defined scope. Ann identified an unrelated misconfiguration and changed it outside the original change request, which caused an outage. Proper change scoping means only the explicitly approved modifica
Question
Options
- ARisk analysis
- BChange board approval
- CScoping the change
- DEnd-user acceptance
Explanation
Change management requires that any approved change be limited strictly to its defined scope. Ann identified an unrelated misconfiguration and changed it outside the original change request, which caused an outage. Proper change scoping means only the explicitly approved modifications are made during a change window. Risk analysis (A) evaluates potential impacts of a change but wouldn't prevent making unplanned changes. Change board approval (B) approves the original scope but doesn't control what happens during execution. End-user acceptance (D) relates to validating the change outcome, not preventing scope creep during implementation.
Community Discussion
No community discussion yet for this question.