220-1002 · Question #184

During the firmware upgrade of a web server, a power outage occurred. The outage caused a failure within the upgrade. Which of the following plans must be implemented to revert back to the most…

The correct answer is A. Backout plan. A backout plan (also called a rollback plan) is a documented, pre-approved procedure specifically designed to undo or reverse a failed change and restore the system to its previous known-good state. In change management, every change should have an associated backout plan…

Hardware and network troubleshooting

Question

During the firmware upgrade of a web server, a power outage occurred. The outage caused a failure within the upgrade. Which of the following plans must be implemented to revert back to the most recent version of the firmware?

Options

  • ABackout plan
  • BContingency plan
  • CAlternative plan
  • DBackup plan

How the community answered

(22 responses)
  • A
    86% (19)
  • B
    5% (1)
  • C
    9% (2)

Explanation

A backout plan (also called a rollback plan) is a documented, pre-approved procedure specifically designed to undo or reverse a failed change and restore the system to its previous known-good state. In change management, every change should have an associated backout plan defined before the change is executed. A contingency plan addresses broader operational disruptions. A backup plan focuses on data preservation and recovery. An alternative plan suggests a different approach to a problem. Only a backout plan specifically addresses reverting a failed upgrade to the prior version.

Topics

#backout plan#firmware upgrade#change management#rollback procedure