nerdexam
Oracle

1Z0-466 · Question #93

Which is true about OUM Manage?

The correct answer is A. It emphasizes clearly documenting the scope of the project and the exact procedures to implement. The Manage focus area is organized into 13 processes: - Bid Transition (A) Scope Management - Financial Management - Work Management - Risk Management - Issue and Problem Management - Staff Management - Communication Management - Quality Management - Configuration Management…

Planning and Scheduling

Question

Which is true about OUM Manage?

Options

  • AIt emphasizes clearly documenting the scope of the project and the exact procedures to implement
  • BIt is not possible to control the project timeline without a detailed project plan.
  • CIt is necessary to only document the items in the scope.
  • DIf the project sponsor requires a functional change, the project team must comply with the request.

How the community answered

(53 responses)
  • A
    74% (39)
  • B
    4% (2)
  • C
    8% (4)
  • D
    15% (8)

Explanation

The Manage focus area is organized into 13 processes: - Bid Transition (A) Scope Management - Financial Management - Work Management - Risk Management - Issue and Problem Management - Staff Management - Communication Management - Quality Management - Configuration Management - Infrastructure Management - Procurement Management - Organizational Change Management Collectively, these processes form a comprehensive set of tasks required to manage Oracle- based development and implementation projects. Every project includes most, if not all, of these processes, whether they are the responsibility of a consulting organization, a client organization, or a third party.

Topics

#OUM Manage#scope documentation#project methodology#implementation procedures