What is the purpose of the Project Execution and Control Phase?

The correct answer is B. To provide adequate visibility into actual progress so that management can take effective actions. Project Execution and Control runs concurrently with the Implement focus area phases. The purpose of the Project Execution and Control Phase is to provide adequate visibility into actual progress so that management can take effective actions when the project's performance…

Project Execution and Control

Question

What is the purpose of the Project Execution and Control Phase?

Options

  • ATo prove the solution described in the scope document meets the project requirements.
  • BTo provide adequate visibility into actual progress so that management can take effective actions
  • CTo successfully transition from the sales team to the delivery team.
  • DTo provide an adequate foundation for the Project Management Plan.

How the community answered

(55 responses)
  • A
    11% (6)
  • B
    82% (45)
  • C
    5% (3)
  • D
    2% (1)

Explanation

Project Execution and Control runs concurrently with the Implement focus area phases. The purpose of the Project Execution and Control Phase is to provide adequate visibility into actual progress so that management can take effective actions when the project's performance deviates significantly from the project plans. The Project Execution and Control Phase includes tracking and reviewing the projects accomplishments and results against documented WBS, project estimates, time schedule, resources plan, and cost budget, and adjusting these plans based on the actual accomplishment and results.